US-54 Traffic Shifts to New Alignment in Seward County

Joe Denoyer - May 24, 2017 10:55 am

Construction continues on the US-54 expansion in Seward County.  With two of the four new lanes completed, the Kansas Department of Transportation, announces that traffic will shift to the newly completed east bound lanes on Thursday, May 25, 2017 while work continues on the new west bound lanes.  Road O will now be opened to the south of 54.

Construction of the west bound lanes continues on this $14.6 million project.  Michels Corporation of Brownsville, Wisconsin is the primary contractor.  The project is expected to be completed by July 2017 weather permitting.  KDOT urges drivers to be alert, pay attention to all work zone warning signs, slow down when approaching a work zone and be prepared to stop.

For more information on this project, please call Greg Adams, Construction Engineer, at 620-629-5797 or Lisa Knoll, KDOT District 6 Public Affairs Manager, at 620-765-7080.

 

Latest Stories

USD 480 Board Meets, May have Potential Buyer for the Old Washington School Property

The USD 480 Board of Education met Monday evening for both a regular meeting and workshop...

SWMC Adds Outpatient Occupational Therapist

  SWMC Press Release: Integrative Physical Therapy at Southwest Medical Center has announced outpatient occupational therapy...

Southwest Miracles 10 Years of Miracles Celebration, Fundraiser this Weekend

The Southwest Miracles annual fundraiser is set for this weekend. The group is celebrating 10 years...