Liberal, KS

Now: 42 °

Currently: Clear

Hi: 62 ° | Lo: 42 °

USD 480 BOE to Vote on Resolution Regarding Lease Purchase Agreement

Joe Denoyer - May 20, 2022 5:11 pm

On Monday, May 23, 2022, the USD 480 Board of Education will vote to adopt Resolution
05-23-22 allowing the school district to enter into a lease purchase agreement for equipment and
improvements. The Facilities Committee has identified two main improvement priorities that
will likely be included in the planned improvements: multipurpose turf activity fields at both
middle schools and repairing the water infiltration problem at the Liberal High School
auditorium. Should these projects be approved, they will be funded through the Capital Outlay
Budget and state aid received by the district will cover the cost of the two middle school fields.
This resolution will allow the school district to borrow up to $7.5 million for equipment and
improvements; however, the recommendations from the Facilities Committee currently total less
than $5 million in total expenditures. The total amount will be set at $7.5 million for this lease
agreement until the LHS auditorium project costs can be finalized in late June.

The projects this lease agreement will address will be formally voted on at the June 6, 2022
board meeting. At that meeting the board will also vote to determine which bank they will be
using for the lease purchases.

The terms of the lease purchase agreement will then be drawn up and a vote will take place to
finalize the agreement at the June 27, 2022 board meeting. It is expected that the agreement will
be closed by the July 20, 2022 board meeting.

Should the lease purchase be approved, it will be funded through the Capital Outlay Fund and
will not increase the total mill levy, avoiding any additional tax burden to the local citizens. Any
increase to the Capital Outlay mill levy will be offset by a reduction in the Supplemental General
Fund and Bond and Interest #1 Fund mill levy. The advantage of using the Capital Outlay Fund
is state aid will cover 45 percent of the cost of the projects. The state aid received by the district
will cover the cost of the two middle school fields.

Moving both middle school activity fields to turf has been made a priority for various reasons,
chief among them being an increase in the rate of usability for each field. Currently, each of our
middle school fields is rated for a total of 30 uses per season during the spring, summer, and fall
according to the Kansas State University Agricultural Experiment Station and Cooperative
Extension Service. This number includes 10 games or activities each season with two practices
prior to each game, with a recommendation for fewer events during the summer season when the
grass is under “heat stress”.

Between the two middle schools there is an average of 618 events on the two fields per school
year, well above the recommended 180 events for the three seasons (see Graph 1). Team
practices and events for both middle schools typically take place at off-campus sites causing
various issues including travel logistics, poor field surface quality, and parent concerns with the
safety of students using fields outside of school property for practice.
Grass requires large amounts of water, fertilizer, herbicide, maintenance and time to recover from
use. Turf provides a year-round surface more durable than grass that can be used for a wide range
of outdoor activities involving a large number of students. Typical life of modern turf in our area
when properly maintained is 10-12 years.

The second project the Facilities Committee has raised concerns about is the auditorium at
Liberal High School. The auditorium has had water infiltration issues for several years despite
attempts to address the problem with a new roof, drainage system, and other repairs.
An in-depth analysis of the structure revealed that the porous bricks used in the initial
construction and other out-dated building methods and materials have led to the high-rate of
water infiltration. The proposed solution for the water infiltration would require the removal and
replacement of all the material on the exterior of the building, from the existing brick down to
the support beams.

These are the two projects the Facilities Committee has designated as their top priorities for the
immediate future. The board, as a whole, will still have to vote on the projects that will be
addressed within this lease agreement. The vote on the projects to be completed will take place at
the June 6, 2022 board meeting.

 

Latest Stories

Redskins Open Guthrie Tournament with a Win

The Liberal Redskin baseball team opened their tournament in Guthrie with a 4-2 win over the...

LHS Esports Qualify for the Spring Playoffs

In a highly competitive field of 800+ participants in the Central Region for Super Smash Brothers...

Boys State of Kansas Offering College Credit, Scholarships for Attendees

The American Legion Boys State of Kansas has announced a partnership with Kansas State University to...

 
KSCB Radio News