US 56 Construction Begins in Elkhart

Joe Denoyer - January 4, 2018 4:17 pm

Grading and surfacing of U.S. 56 at Morton Street in Elkhart could begin as early as January 8. This project includes the reconstruction of Morton Street intersection on the north side of U.S. 56 with the addition of a turn lane on U.S. 56. Morton Street, north of the highway will be closed at the intersection and will require an alternate route during the project. Morton Street, south of U.S. 56 will remain open during the project.
Bryant & Bryant of Halstead is the contractor on this $536,468 project which is expected to be completed by March 16 weather permitting.
For more information on this project, contact Greg Adams, Construction Manager, at (620) 624-4451 or Lisa Knoll, KDOT District 6 Public Affairs Manager, at 620-765-7080.

 

Latest Stories

National Day of Prayer Today

A National Day of Prayer event will take place Thursday, May the 2nd at the stage...

SCCC Graduation is This Weekend

Seward County Community College will hold it’s 53rd Annual Commencement on Saturday, May 4th. There will...

April Total Tax Collections Nearly 8.0% Above the Estimate

April Total Tax Collections Nearly 8.0% Above the Estimate TOPEKA – Governor Laura Kelly today announced...

 
KSCB Radio News