Update on the four-lane expansion project in Seward County.

Joe Denoyer - October 14, 2023 6:20 pm

Koss Construction opened U.S. 54 to unrestricted traffic today around 5:30 p.m. Koss Construction will continue to close sections of this roadway over the next few weeks to fine-tune the project.

County Road 7 will still be closed at U.S. 54 due to a missing railroad crossing signal. The railroad has indicated the equipment will be installed in early November.

The final phase of County Road M-7 will be open end of next week.

This project is estimated to be complete in November.

 

Latest Stories

Candidate Filing for Seward County May 10

Candidate Filing for Seward County May 10, 2024 2024 AUGUST PRIMARY SEWARD COUNTY COMMISSION DIST 1...

Liberal Retains Essential Air Service Program Designation

An executive order issued this month by the U.S. Department of Transportation extends Essential Air Service...

Texas County Accident Sends Three to the Hospital

An injury accident occurred on Thursday evening at approximately 5:00 pm on US-64 and Mile 14,...

 
KSCB Radio News